Skip to main content

Projects

Nickel Acid Leaching Plant

Nickel Atmospheric Acid Leaching Processing Plant

Where We Are?

Kolaka City, Southeast Sulawesi Province, Indonesia

Project Site Area

A Total Of

12
hectare

Facilities

17%

Ore Stockpile

83%

*Land clearing completed

Strategic Location with Connectivity

National Road Access

Jetty (5 km)

Water Source for Operation from a River Near the Site

Airport (60 km)

Production Capacity

4000
MTPA (as Ni 99% Base)
6320
MTPA (as Ni (OH)2)

By-products

69,487
MgO
85,187
Iron Oxide
127,260
Silica

Input Capacity

Laterite Nickel Ore (Ni ± 1.3%)
435,800 MTPA (Wet Feed Ore Base)

Advancing Nickel Extraction with Atmospheric Acid Leaching (AAL) using Hydrochloric Acid (HCl)

EPCC

32
Months

(20 months for construction)

Operation

20
Years

Plant Unit Installed

Integrated Nickel AAL Processing System
Slurry Leaching & HCl Recovery System
Indirect Heating Rotary Kiln System
Building and Support Facility
Raw Material Feeding System
Package Equipment
Purification System
Utility Facilities

Comparison of Nickel Extraction Process

Smelting HPAL
(High Pressure Acid Leach)
AAL
(Atmospheric Acid Leaching using HCl)
Raw Material Sulfide ore Laterite Ore Laterite Ore
Technology Production of ferronickel by smelting / reduction process Nickel concentrates by acid leaching at high temp. (250~270 °C), high press. (40~50 bar) Nickel concentration and other product from waste at atmospheric pressure and normal temp. (AMB~80 °C)
Process Nickel ore → Drying → Preliminary reduction → Melting furnace (>1,500 °C) → Reduction → Separation of FeNi & Slag → Refining → Casting → FeNi Nickel ore → Water mixing → Autoclave → Neutralization → Precipitation of sulfide metal → Autoclave → Solvent extraction → Autoclave (hydrogen reduction) → Ni powder Nickel ore → Acid leaching → 1st purification → 2nd purification → Highly concentrated Ni, Nickel Hydroxide
CAPEX 400 200 100
Final Product Fe-Ni Ni metal Nickel Hydroxide, Iron Oxide, SiO₂, MgO
Purity of final nickel related products Fe-Ni: 20% Nickel Metal: 99% Nickel Hydroxide: > 90%
Nickel Sulfate: 99.9%
Key Features Initial TIC: Very high
Operating Power: Very High
Operation Steps: Simple
By-Products: Low
Initial TIC: High
Operating Power: High
Operation Steps: Complicate
By-Products: Low
Initial TIC: Low
Operating Power: Low
Operation Steps: Simple
By-Products: High
Energy Consumption & Emissions High Middle Low
Wastewater & Waste Fe-Ni Slag (>90% of feed) & Many wastewater Many acidic wastewater Waste-free process.
ZLD (Zero Liquid Discharge)